Our firm rehabilitated approximately 3,500 linear feet of 54-inch gravity pipeline, associated manholes, and the 26th Street Siphon in Newport News, Virginia.

Our firm rehabilitated approximately 3,500 linear feet of 54-inch gravity pipeline, associated manholes, and the 26th Street Siphon in Newport News, Virginia.

Client
Hampton Roads Sanitation District
Owner
Hampton Roads Sanitation District
Location
Newport News, Virginia
Markets
Water
Completed
2021
Region
Mid-Atlantic

Our firm provided preliminary engineering, design, permitting, and construction phase services for Hampton Roads Sanitation District (HRSD) to rehabilitate approximately 3,500 linear feet of 54-inch gravity pipeline, associated manholes, and the 26th Street Siphon. Given the location of the sewer in the highly traveled corridor of Jefferson Avenue, we evaluated the critical elements of available sewer repair methods, bypass pumping alternatives, and traffic control in conjunction with a triple bottom line analysis to balance social, environmental, and cost impacts to deliver a quality and successful project.

The evaluation and design completed for this project included a thorough review of available condition assessment data, analysis of flow data and historical wet weather flow, research of rehab methods suitable for the large diameter pipe and large concrete structures, design of an extensive 26-million-gallon-per-day bypass pumping operation for full pipe capacity, and comprehensive coordination with the Virginia Department of Transportation for traffic control measures for the exit and entrance ramps to I-664 and with the City of Newport News for traffic control measures along the city streets. The rehabilitation consisted of large diameter cured-in-place pipe for the 54-inch gravity sewer and spray-applied epoxy lining system for the siphon renewal as well as manhole rehabilitation along Jefferson Avenue and Terminal Avenue.

3,500

linear feet of gravity sewer rehabilitation

54

inch gravity sewer pipe

26

million gallon per day bypass