Skip to Content

University of Pittsburgh Medical Center Mercy Hospital

Retro-Commissioning a Tertiary Acute Care Teaching Hospital

The tertiary acute care teaching hospital is the region’s only trauma and burn center and welcomes 1,650 newborns annually.

The tertiary acute care teaching hospital is the region’s only trauma and burn center and welcomes 1,650 newborns annually.

Our team analyzed available system trends from building automation systems (BAS) to log, categorize, and prioritize issues, all of which were remedied during installation.

Our team analyzed available system trends from building automation systems (BAS) to log, categorize, and prioritize issues, all of which were remedied during installation.

We optimized the chiller plant by automatically staging five chillers, pumps, and cooling towers and programming chilled water system supply setpoints to reset based on downstream AHU valve positions.

We optimized the chiller plant by automatically staging five chillers, pumps, and cooling towers and programming chilled water system supply setpoints to reset based on downstream AHU valve positions.

A condensed water temperature setpoint strategy was programmed for a cooling tower that decreased the chilled water system's energy use.

A condensed water temperature setpoint strategy was programmed for a cooling tower that decreased the chilled water system's energy use.

We increased BAS reliability and facilitated more advanced control sequences by managing two pneumatic AHU upgrades to direct digital control.

We increased BAS reliability and facilitated more advanced control sequences by managing two pneumatic AHU upgrades to direct digital control.

Variable frequency drives and new premium efficiency motors were installed where existing vane air flow control methods were found functionally incorrect.

Variable frequency drives and new premium efficiency motors were installed where existing vane air flow control methods were found functionally incorrect.

Damper replacements improved outside air control with limited equipment downtime.

Damper replacements improved outside air control with limited equipment downtime.

Owner/Client
University of Pittsburgh Medical Center
Location
Pittsburgh, Pennsylvania
Square Footage
996,000 SF
Cost
$597,000
Completed
2015
Region
Northeast

We retro-commissioned the University of Pittsburgh Medical Center’s (UPMC) 495-bed Mercy Hospital.

After investigating current facility operations and equipment, we recommended five energy-reducing strategies. Our team implemented upgrades to the BAS, optimized air handling unit (AHU) controls, replaced AHU dampers, installed and programmed variable frequency drives, and optimized chilled and condenser water system stages and operations. Working with hospital facility management, we determined critical areas that require constant air flow and placed hundreds of terminal units and dozens of AHUs on customized schedules or overnight setback, programmed occupant overrides, standardized and optimized AHU economizer sequences, and set supply air temperature points for AHUs under a reset schedule based on outside or return temperatures.

Following construction, we scheduled a measurement and verification (M&V) period to track energy savings so utility incentives could be disbursed, further reducing simple payback.

1,915,000 kWh

annual electrical energy savings

93,190 therms

annual gas savings

$181,730

annual savings

Related Projects