Skip to Content

Route 7/River Creek Parkway Interchange

Connecting the Community

The project included re-alignment and grade separation of River Creek Parkway from its previous at-grade connection with Route 7, the extension of River Creek Parkway south of Route 7, and re-alignment of several connecting roadways.

The project included re-alignment and grade separation of River Creek Parkway from its previous at-grade connection with Route 7, the extension of River Creek Parkway south of Route 7, and re-alignment of several connecting roadways.

We designed a modified spread diamond configuration for the interchange to maximize the development area and facilitate the possible addition of flyover ramps, which could support a future crossing of the Potomac River by River Creek Parkway.

We designed a modified spread diamond configuration for the interchange to maximize the development area and facilitate the possible addition of flyover ramps, which could support a future crossing of the Potomac River by River Creek Parkway.

We coordinated multiple parties—neighboring home owners associations, the Board of Architectural Review, and the Leesburg Board of Supervisors—to incorporate design refinements and enhancements throughout plan development.

We coordinated multiple parties—neighboring home owners associations, the Board of Architectural Review, and the Leesburg Board of Supervisors—to incorporate design refinements and enhancements throughout plan development.

Client
Kettler
Owner
Konaig
Location
McLean, Virginia
Markets
Transportation
Cost
$24 million
Completed
2008
Region
Mid-Atlantic

As a key component of an overall development plan in Leesburg, Virginia, we provided design and construction services for the Route 7 and River Creek Parkway Interchange. Privately funded, the interchange provides primary access to the Village at Leesburg, a mixed-use urban community with housing, national retail chains, and restaurants.

Selected from a series of conceptual design studies which compared access alternatives, we factored in the following criteria:

  • traffic and various interchange configurations with respect to the client’s needs and VDOT approval
  • features to enhance adjacent communities
  • impacts to adjacent historic and natural resources
  • stormwater management
  • significant utility conflicts and relocation
  • architectural features