Skip to Content

Route 56 Rainbow Lake Dam Emergency Bridge Repairs

Rising to the Challenge

With the construction of the new 200-foot-long semi-circular spillway, 110-foot-long two-span bridge, and restored dam/roadway, we returned the beauty of Rainbow Lake to the community.

With the construction of the new 200-foot-long semi-circular spillway, 110-foot-long two-span bridge, and restored dam/roadway, we returned the beauty of Rainbow Lake to the community.

Initial utility, demolition, and stream diversion work was completed within three weeks of the storm. We recommended that NJDOT advertise the contract with 20 lump sum items to expedite construction—the first of its kind for NJDOT.

Initial utility, demolition, and stream diversion work was completed within three weeks of the storm. We recommended that NJDOT advertise the contract with 20 lump sum items to expedite construction—the first of its kind for NJDOT.

Cast-in-place piles were poured inside a cofferdam at the 200-foot-long semi-circular ogee weir spillway. Working closely with the contractor, we processed shop drawings in about two-days-time to stay on schedule.

Cast-in-place piles were poured inside a cofferdam at the 200-foot-long semi-circular ogee weir spillway. Working closely with the contractor, we processed shop drawings in about two-days-time to stay on schedule.

Adding a modern mechanical sluice gate to the new spillway allows the NJDEP to regulate the lake level more closely.

Adding a modern mechanical sluice gate to the new spillway allows the NJDEP to regulate the lake level more closely.

Owner/Client
New Jersey Department of Transportation
Location
Pittsgrove, New Jersey
Markets
Transportation
Cost
$4.5 million
Completed
2007
Region
Northeast

When a nor’easter caused Rainbow Lake in Pittsgrove, New Jersey, to overtop Route 56, NJDOT called us to design the $4.5 million emergency repairs. Working over weekends and holidays, we designed the repairs in four weeks, which ultimately resulted in reopening the bridge six weeks ahead of schedule. We developed a complex detour route and signage scheme that allowed the project to proceed concurrently with adjacent work, while minimizing impacts to the community.

$4.5 million

emergency repairs

Awards

  • Distinguished Award for Excellence

    ACEC New Jersey

  • Outstanding Civil Engineering Project of the Year

    ASCE New Jersey

Related Projects