Garden State Parkway Shoulder Restoration and Improvements MP 83 to 100 Program Manager Services

Improving Safety and Traffic Flow along the Garden State Parkway

The purpose of the $330 million project is to improve safety and enhance emergency response along this section of the Garden State Parkway by increasing the shoulder width.

The purpose of the $330 million project is to improve safety and enhance emergency response along this section of the Garden State Parkway by increasing the shoulder width.

We were required to apply for five permits from the New Jersey Department of Environmental Protection (NJDEP) and approvals from NJDEP and local planning boards.

We were required to apply for five permits from the New Jersey Department of Environmental Protection (NJDEP) and approvals from NJDEP and local planning boards.

We managed the program and coordinated with the NJTA; the New Jersey Department of Transportation; Ocean and Monmouth Counties; municipalities; utilities; regulatory agencies; and the public.

We managed the program and coordinated with the NJTA; the New Jersey Department of Transportation; Ocean and Monmouth Counties; municipalities; utilities; regulatory agencies; and the public.

Client
New Jersey Turnpike Authority
Location
Ocean and Monmouth Counties, New Jersey
Markets
Transportation
Cost
$330 million
Completed
2014
Region
Northeast

As part of an effort to improve safety and traffic flow conditions, the New Jersey Turnpike Authority (NJTA) decided to widen 17 miles of highway, including 31 bridges (two new, 20 replacements, and nine superstructure elements) in Ocean and Monmouth Counties, New Jersey. We delivered program management services to the NJTA, overseeing a $330 million project which involved four design engineers, and four contractors, and required coordination with two nearby Ocean County interchange projects.

We established an effective management process for design reviews, revisions, and quality control that enabled the project to gain necessary regulatory approvals and meet schedule milestones. This was made possible because of our deep client knowledge including their policies and procedures, governing regulations and regulatory agencies, and engineer and contractor practices. Our established program also accommodated challenges including a necessary redesign due to Hurricane Irene flooding and design engineer contracts that were not aligned with the construction contracts.

17

miles of roads widened

31

bridges widened

2

bridges added

20

bridge replacements