McElvey Transmission Main

Creating an Emergency Above Ground Water Main Solution
Bay County, Florida

When Hathaway Bridge was constructed in 2003 to replace the Saint Andrews Bay Bridge, a 24-inch ductile iron pipe was constructed and supported within the bridge spans. In early 2018, a water leak developed in the 24-inch ductile iron transmission main near the east end of the bridge. Under an emergency work order and under contract from Bay County with our design-build teaming partners at Marshall Brothers Construction, we evaluated feasible alternatives to construct a temporary bypass transmission water main that would allow Bay County to assess the extent of the water leak and alternatives for repairs, while at the same time provide a backup water supply.

14 days

to complete the design

We were tasked with designing the temporary bypass line to convey peak water demand to the Panama City Beach McElvey storage pump station, evaluate various pipe materials for construction, and develop construction drawings. The proposed alignment for the temporary bypass transmission main included approximately 6,000 feet of water main with a portion of the water line to be buried, but the majority of the pipe to be laid on top of the concrete sidewalk and pedestrian bridge deck along the bridge span. Pipe expansion joints were also incorporated near the bridge expansion joints.

Client

Bay County, Florida

Cost

$100,000

Services

  • Engineering

Markets

  • Risk, Response and Recovery
  • Water

Regions

  • Southeast